CLIENT: BMD URBAN
CONTRACT TYPE: SCHEDULE OF RATES
COMPLETION DATE: ONGOING
PROJECT OVERVIEW
ACM has been contracted to construct a two-lane bridge at the entry to the Ripley Providence Development in the Ripley Valley, Ipswich.
The bridge is a three span concrete structure over Bundamba Creek, providing a vehicular, pedestrian and service corridor to the Development.
ACM SCOPE OF WORKS
ACM is responsible for the supply of all labour, plant, equipment and temporary materials associated with the completion of the following elements;
- Construction of all concrete formwork
- Placement of concrete reinforcement
- Placement and finishing of concrete
- Temporary works engineering and construction
- Installation of bridge deck units
- Erection of the bridge furniture, including the bridge guardrail
- Supply of ACM plant and equipment for site material handling including cranage
- Construction of the RCP and RCBC culvert base slabs headwalls and end walls